Weekly Update #42, 30 July 2021
DCIM100MEDIADJI_0005.JPG

Weekly Update #42, 30 July 2021

Author: Jason Bush Dan Heidt, of Home Insulation Company informed me that they were able to get the under-floor insulation installed, and took the time to do a take-off of…

Continue Reading Weekly Update #42, 30 July 2021
Weekly Update #41, 23 July 2021
Chris Carpenter, Springfield B. O. and me

Weekly Update #41, 23 July 2021

Author: Jason Bush Dan Wilson was able to come out Monday and get our power and LPG trenches in, and Superior Electric came out Tuesday and installed the conduit. We…

Continue Reading Weekly Update #41, 23 July 2021
Weekly Update #40, 16 July 2021
North

Weekly Update #40, 16 July 2021

Author: Jason BushCoast Fork Construction will be finishing up the framing this Saturday. I will be out there most the day organizing, painting cabinets on the sub-floor, evaluating our job-site…

Continue Reading Weekly Update #40, 16 July 2021
Weekly Update #39, 9 July 2021
Jayson perusing his new kitchen area.

Weekly Update #39, 9 July 2021

Author: Jason Bush Coast Fork Construction continues the work on sheathing the gable ends, adding fascia, out lookers, and over framing of the roof. I am barely staying ahead of…

Continue Reading Weekly Update #39, 9 July 2021
Weekly Update #35, 11 Jun 2021
The following picture is one of my favorites as I unexpectedly came upon Misty and Jayson looking over their new home floor plan. They want everyone to know how thankful they are. How they have finally allowed some excitement to seep through this terrible situation that will end up enduring almost three years of their life.

Weekly Update #35, 11 Jun 2021

Author: Jason BushThe existing house has again settled with additional floor movement, more cracks in the sheetrock, and the issue of the window that fractured from compression stress. One of…

Continue Reading Weekly Update #35, 11 Jun 2021