Read more about the article Weekly Update #53, 15 Oct 2021
In the picture above you can see the built-up grade at the front porch, as well as the posts that require elevated. In the pictures below, it can be seen that we are getting pretty close to final elevations at the back porches. We still need to compact the last lift, before piling anymore on.

Weekly Update #53, 15 Oct 2021

Author: Jason BushWe heard back from Jim Johnson, of Hamilton Drywall Products which is based in Woodlawn, Washington. Jim called and said they were putting the materials together, and Donnie…

Continue ReadingWeekly Update #53, 15 Oct 2021
Read more about the article Weekly Update #50 & 51, 1 Oct 2021
The picture above shows the compacted ¾” minus rock and soil that is imported to contain it in order to build up the back porch area to meet ADA Wheelchair Standards. The far area will eventually support a therapy & exercising spa.

Weekly Update #50 & 51, 1 Oct 2021

Author: Jason Bush It was decided to skip last week’s update, as there was not a lot to report. The ICC Annual Business Meeting went good. I did much of…

Continue ReadingWeekly Update #50 & 51, 1 Oct 2021